Dependency Mapper for monday.com

Turn any monday board into a Primavera P6-style schedule: the critical path, total float, a schedule health check, impact-checked rescheduling, baselines, and an automation that stops work starting before what it depends on is done.

monday.com · Board view · Dependency Graph
The Dependency Graph view: summary cards, toolbar, an activity table and a Gantt chart with red critical bars and links between activities
Any boardPick your own columns. Nothing is hard-coded.
10 checksA schedule health score based on DCMA’s 14 points
Impact firstSee what a move does before a date changes
EnforcedStarting early is undone automatically
Overview

What Dependency Mapper does

monday’s Dependency column links items, but it doesn’t tell you which work drives the finish date, how much room each item has, or what a change will do. Dependency Mapper adds a board view and an automation that answer those questions the way a planner would in Primavera P6.

Everything works on any board you choose. You pick the columns in the view’s settings, so the app never assumes your board’s layout.

Quick start · about 2 minutes

Get started in 4 steps

Tick each step as you go. Your progress is saved in this browser.

  1. Install the app

    Install Dependency Mapper from the monday.com apps marketplace. New installs start with a 14-day Business trial, so every feature is on while you try it.

  2. Prepare a board

    Use a board with a Dependency column, a Timeline column and a Status column. In the Dependency column’s settings, choose a dependency type (Strict or Flexible): monday hides the links until one is set.

  3. Add the view

    Click + next to the board’s views, choose Apps, then Dependency Graph. The view picks your columns automatically.

  4. Check the columns

    Open the view’s Settings to confirm the Dependency, Timeline and Status columns, and optionally add an Activity ID (text), % complete (numbers) and Baseline (timeline) column.

0 of 4 done
An item counts as done when its status is one of the column’s done labels: the labels marked as done in monday’s status settings, such as Done.
The view

A tour of the Dependency Graph view

Click a numbered marker to see what each part does, or step through them in order.

The Dependency Graph view with numbered markers
    The view

    The summary cards

    Six cards above the chart answer “where are we?” at a glance. Critical, Late and Starting soon are also filters: click one to show only those activities (a Filtering tag appears), and click again to show everything.

    The summary cards on a sample fit-out project.
    CardWhat it shows
    CompletePercent complete across the schedule, weighted by each activity’s duration, so a 30-day activity counts for more than a 2-day one. Shows how many activities are done.
    Project finishThe latest planned finish, how many days away it is, and (with a baseline) how many days it sits ahead of or behind the baseline.
    CriticalOpen activities with no total float left. Click to filter.
    LateOpen activities whose finish date has passed. Click to filter.
    Starting soonOpen activities due to start in the next 14 days. Click for a two-week look-ahead.
    HealthThe schedule health score. Click for the checks.
    Clicking Critical shows just the activities with no float left.
    The view

    Reading the schedule

    The left side is a P6-style activity table; the right is the Gantt chart, with months above weeks (or days, or months above years). Board groups become WBS bands with a summary bar that fills as the group progresses. Click a group to collapse it, and click an activity’s name or bar to open the monday item.

    Critical path and float

    Every link is finish-to-start. Dependency Mapper works backwards from the project finish to find each activity’s total float: how many days it can slip before the finish moves. Activities with 0 days or less are on the critical path and drawn in red. Negative float means the plan already misses its own dates.

    Trace a chain

    Hover over (or tab to) any bar. Everything it depends on, and everything that depends on it, stays bright with its links drawn in blue; everything else fades back. The hover card shows the dates, duration, status, float, change against the baseline and how many links come before and after.

    Hovering Services design traces the chain from Site survey through to delivery.

    What the shapes mean

    Activity. The darker part is % complete.
    Critical: no float left
    Milestone (a one-day item)
    Late: open and past its finish
    Baseline dates (Pro)
    Group summary, filled by progress
    Finish-to-start link
    Today, the data date
    Items without Timeline dates aren’t drawn. The status line under the toolbar says how many there are, and the health check lists them.
    The view

    Filters, zoom and layout

    ControlWhat it does
    SearchMatches Activity ID, name, group or status as you type. × clears it.
    GroupsShows one board group.
    Look-aheadThe next 2 weeks, 4 weeks or 3 months, as a P6 look-ahead layout.
    Hide completedHides activities with a done status.
    Clear filtersAppears whenever something is filtered, and shows everything again.
    TodayScrolls the timescale back to today.
    Days · Weeks · MonthsThe timescale zoom.
    ViewLayout options and which columns to show (below).
    ⟳Reads the board again.

    The View menu

    • Group by board group: WBS bands on, or one sorted list.
    • Show baseline bars (Pro, once a baseline is set).
    • Collapse all / Expand all groups.
    • Columns: Activity ID, Orig Dur, Start, Finish, Total Float, %, Status, BL Start, BL Finish, BL Var and Preds.
    • Reset layout back to the default.

    Click any column heading to sort: ascending, then descending, then back to the original order. Your layout is remembered for each board in your browser.

    Insight

    Schedule health check FreeDetails in Pro

    The Health card scores the schedule out of 100: the share of quality checks that pass. The checks follow the DCMA 14-point assessment, cut down to what a monday board can hold. A score of 90 or more is healthy, 70 or more needs attention, and anything lower needs work.

    On Pro and Business, open a check to see which activities fail it. Click one to open the item, or Show these on the chart to filter the Gantt to them. Export CSV downloads the full report.

    The checks, and how to fix them

    Pick a check to see what it looks for and what to do in monday.

    “Allowed” is a share of the open, dated activities. For example, with 40 of them, 5% allows 2 open ends before the check fails.
    AI

    Ask Dependency Mapper Free

    Click Ask in the bottom-right corner of the view to ask about the schedule in plain words. Answers come from the schedule on screen, worked out with the same maths as the view, and name the activities they’re about. Click one to open the item.

    Asking what a week’s slip on Structural design would do. Nothing on the board changes.

    Things to ask:

    • “What’s blocking Fit-out?” lists the predecessors that aren’t done yet.
    • “What’s on the critical path?” lists the activities that set the finish date.
    • “If Demolition slips 5 days, when do we finish?” gives the new dates, the float used and what else would move.
    • “What depends on Development approval?”, “What’s late?” and “What starts in the next two weeks?”
    • “How healthy is this schedule?” gives the health score and the checks that fail. Pro and Business also list which activities fail them.
    • “How do I set a baseline?” and other questions about using the app.

    Ask only reads the schedule; it never changes a date or status. It runs on monday AI, so it uses your account’s monday AI credits, and it’s on every plan. Answers can be wrong, so check before you change anything. The conversation stays until you reload the view; New chat starts again.

    Acting on it

    Drag to reschedule, with an impact check Pro

    Drag a bar to move an activity, or drag its right end to change only the finish. While you drag, the new dates follow the bar.

    When you let go, nothing has changed yet. You first see what the move does: the before and after dates, the float used, whether the project finish moves, the change against the baseline, and which linked items monday would shift. Reschedule writes the new dates to the board; Cancel leaves everything as it was.

    On Free, the impact check still opens with the real numbers, and its button offers Pro instead of saving. Viewers and guests can read the schedule but can’t drag bars or set a baseline.
    Acting on it

    Baselines and variance Pro

    Set baseline copies today’s planned dates into a Baseline timeline column: the one chosen in the view’s settings, or a new “Baseline” column it creates. From then on:

    • a gold bar under each activity shows its baseline dates;
    • the BL Start, BL Finish and BL Var columns (in the View menu) show the variance in days, where + means later than planned;
    • the Project finish card shows the whole project’s variance, and the health check adds Missed baseline finish.

    Update baseline replaces it with the current plan. It asks first and tells you how many items it will copy.

    Automation

    Enforce dependencies Business

    monday can’t stop a status change before it happens, so Dependency Mapper undoes it straight afterwards. When someone starts an item before everything it depends on is done, the app puts the status back and posts an update explaining why. Step through what happens:

    DMDependency Mapper · just now
    @Alex Chen Framing can’t be Working on it yet. It’s waiting on Foundations, which isn’t done. The status has been put back.

    Set it up

    1. On the board, open Automate and add the Dependency Mapper automation. It reads: When Status changes to Working on it, only allow Working on it once every item in Dependencies is done
    2. Choose your Status column, the status that means work has started, and your Dependency column. If the board has only one Dependency column you can leave it blank.
    3. Use the same status in the trigger and in the action. Don’t set the trigger to “changes to anything”.
    The update mentions whoever made the change, so they get a notification. monday doesn’t notify you about your own mention, so test it with a second person.

    If it doesn’t run

    Open the automation’s activity log. A message from Dependency Mapper says what to change, for example “This board has more than one dependency column. Choose which one in the automation.” If it says “Enforcement is part of Dependency Mapper Business”, the account isn’t on Business or a trial.

    Plans

    Plans

    Seeing your schedule is free. Changing the plan, and enforcing it, are paid. Change plans from the app’s page in the monday marketplace.

    FeatureFreeProBusiness
    Schedule view, critical path, float, filters, look-aheadOne boardEvery boardEvery board
    Summary cards and chain tracing✓✓✓
    Schedule health score and counts✓✓✓
    Health findings, show on chart, CSV export–✓✓
    Drag to reschedule with the impact checkPreview only✓✓
    Baselines and variance–✓✓
    Enforce dependencies automation––✓

    Free covers the first board you use the view on. On another board, the schedule shows for a few seconds and then offers Pro, or to move Free to that board with Use it on this board instead.

    Help

    Troubleshooting and FAQ

    The view says “Check the view settings”

    A chosen column was deleted, or is the wrong type. Open the view’s Settings and choose a Dependency, Timeline and Status column again. The message names the column that needs changing.

    What is the yellow “Check the schedule” warning?

    It lists problems in the board’s own links: loops, links to deleted items, items planned to start before a predecessor finishes, and items with no dates. Close it with × and it stays closed until the problems change. The health check covers the same problems and more.

    Why is a bar drawn later than its dates?

    It’s planned to start before something it depends on finishes, so the chart shows it at the earliest date the links allow. Move its start, or remove the link, to fix it.

    I can’t drag bars or set a baseline

    Viewers and guests can read the schedule but not change it. On Free, dragging opens the impact check but saving needs Pro. Baselines need Pro.

    Does it work in dark mode?

    Yes. It follows monday’s light, dark and night themes.

    How does it know an item is done?

    From the status column’s done labels: in monday’s status settings, the labels marked as done. A done item shows 100% and is greyed out on the chart.

    Does it use working days or holidays?

    Not yet. Durations and float are in calendar days.

    Trust

    Your data

    Dependency Mapper reads your board through monday’s API and doesn’t store item data on our servers. Its server runs on monday code, monday.com’s own hosting. Ask Dependency Mapper sends your question and the schedule details it needs to monday AI, inside monday; it doesn’t go to Quirk or any other AI provider. Your layout choices are kept in your own browser. We record which features are used (such as “the view opened”), with your account ID and no item names or content. See our Privacy Policy and Terms of service.

    Need a hand?Quirk builds and supports Dependency Mapper, and we’re a monday.com partner if you’d like help setting up your schedules.