Case study · Atlassian migration

How a telecommunications provider moved every team from Asana to Jira Cloud over the holiday break

58 projects, their history and their workflows moved into Jira Cloud inside a network change freeze, so the whole company could start the new year on one platform.

Engineering and IT team working together at their desks
58 projectsmigrated with history validated
1 platformfor every team in the company
IndustryTelecommunications and fibre networks
SizeMid-sized, multi-site Australian team
PlatformJira Cloud (Atlassian)
EngagementFixed scope, December 2025 to January 2026
DeliveryDuring the holiday network change freeze

Results at a glance

A clean cutover while the network was frozen

58Asana projects migrated into Jira Cloud with history validated
2.5 weekscutover window inside the holiday change freeze
1 platformfor network engineering, IT, operations and corporate teams

The challenge

Licences for everyone, real use by a few

This engineering-led Australian telco runs its own network and serves business and consumer customers. Its teams worked in very different ways: some waterfall, some Kanban, and only IT ran Scrum. Asana was licensed for the whole company, but in the month before the move only about ten people had logged in, and much of it was personal to-do lists with statuses used as categories.

Jira Cloud already existed but held mostly test projects, while the service and order desks ran on separate platforms. Leadership wanted one place where work could be shared and tracked across teams, and better reporting on what each team was delivering.

Our approach

Plan the whole journey, deliver the first step well

Quirk scoped a three-horizon roadmap covering work management, the service desk and the move off Data Center. The client chose to start with Horizon 1 and keep its other platforms in place for now.

March to June 2025

Discovery and roadmap

Scoping calls, a technical walkthrough with Quirk's Jira Service Management specialist and a three-horizon proposal, then a focused Horizon 1 scope.

November 2025

Plan the cutover

A planning session to fit the migration inside the network change freeze and agree what to keep, clean up and archive.

December 2025 to January 2026

Migrate and validate

Status and field mapping to cut bloat, standardised workflows and boards, with project history kept and validated.

January 2026

Launch and reconcile

A client-led run-through for staff, then a second pass that brought across private projects and reconciled every ticket.

What we built

A Jira Cloud site built for how each team works

Mapped statuses and fields

Asana's category-style statuses mapped to real workflow states, and unused fields removed rather than copied across.

Standardised boards and workflows

Consistent workflows and boards per team, so Kanban and project teams can share reporting.

History preserved and validated

Project history moved across and checked, so nothing was lost in the switch.

Migration summary in Confluence

A record of every project moved, the approach, outcomes and next steps for the client's own team.

Launch session for staff

The client's systems lead walked teams through Jira the day after cutover, using material from the migration.

Read-only fallback

Asana kept read-only on a minimal plan for three to six months, so anyone could check old work without paying for full licences.

Staff learning a new work management platform at their computers

Change without disruption

Teams left for the holidays in Asana and came back to Jira

Doing the move during the network change freeze meant no competing priorities and no interruption to customer work.

The results

One platform and no complaints

The first 25 projects were live in Jira by 5 January 2026, a further 33 private projects followed four days later, and staff joined a run-through on day one. The client's IT lead reported he had not heard a single complaint from the team, which he noted was unusual for a tool change.

A post-cutover reconciliation found that private Asana projects had been hidden from the migration account. Those projects and around 120 tickets were brought across and validated by the end of January, so the record is complete.

AreaBeforeAfter
PlatformAsana, Jira Cloud and separate desksOne Jira Cloud site for every team
StatusesUsed as categoriesMapped to real workflow states
UsageAbout ten active users in a monthCompany-wide launch on day one
HistoryLocked in old projectsMigrated and validated in Jira
Old toolFull licences for everyoneRead-only fallback on a minimal plan

Lessons for your team

What other teams moving off Asana can take from this

Check private projects first

Make sure the migration account can see private projects before cutover, not after.

Use a natural pause

A change freeze or holiday period gives you a clean break without competing priorities.

Don't copy the clutter

Map statuses and fields to how work should run, and leave the rest behind.

Free 30-minute system review

Planning a move to Jira or Atlassian Cloud?

We'll review your setup live, name the three biggest risks and recommend a migration path. You keep the findings either way.

FAQs

Questions about moving from Asana to Jira

How long does an Asana to Jira migration take?

Here, 58 projects moved over about two and a half weeks, with a reconciliation pass afterwards. Planning the field and status mapping takes longer than the move itself.

Will we lose our Asana history?

No, if it is planned. Project history can be migrated and validated, and keeping Asana read-only for a few months gives people a safety net.

Should we use Jira or monday.com for non-software teams?

Both work. Jira suits engineering-led organisations already on Atlassian, while monday.com is often quicker for business teams. Quirk partners with both, so we recommend based on your teams.

Do we also need to move off Atlassian Data Center?

Data Center reaches end of life, so most organisations need a plan. See Atlassian Data Center end of life for options and timing.

50+monday.com and Atlassian projects delivered in the last 12 months
5/5Recent client satisfaction score (CSAT)
15+Years delivering quality outcomes across APAC

See what your system of work could look like.

We'll review your current setup live, name the three biggest gaps and recommend a next step. You keep the findings either way.